CFMEU ‘enjoy a significant level of influence’ over Victorian government, Big Build royal commission hears
Özet haber: Inquiry into allegations of corruption begins block of hearings focused on 2022 level crossing removal project

Inquiry into allegations of corruption begins block of hearings focused on 2022 level crossing removal project
Get our breaking news email, free app or daily news podcast
The royal commission into allegations of corruption on Victorian Big Build projects has heard a major construction company feared putting the Construction, Forestry and Maritime Employees Union (CFMEU) offside because of its close links to the Daniel Andrews Labor government.
The first block of hearings under the commission into the integrity of major public and civil infrastructure construction projects in Victoria will hear evidence about the union’s involvement in a level crossing removal project at Gap Road in Sunbury, north of Melbourne, in 2022.
The project involved the removal of a level crossing and the construction of a new rail bridge and underpass.
The counsel assisting the commission, Chris Young KC, said 20 witnesses have been compelled to appear during the November hearings.
But he warned that others were not complying with orders to produce documents to the commission, including using the excuse of “government policy” to delay their production. Failing to comply with such orders is a criminal offence.
“It is extremely concerning that some parties have not complied with the terms of those notices to produce,” Young said.
The hearings in November will focus on what government officials did during a June 2022 meeting in order to appease the union, who had forced work to stop on the Gap Road project.
Young showed the commission evidence that – in the years before the union interfered in the project – there was increasing awareness within the construction sector about the prospect of industrial action curtailing work, and the growing influence of the CFMEU.
He said that in 2017, one of the companies involved in the Gap Road project, John Holland, noted that the CFMEU was “proud of the fact that none of their site visits are code compliant”.
It also noted in an email the “significance of the CFMEU relationship with the Andrews government in Victoria, and the impact this is having, and will have in the future, in respect of client relationships with the Victorian government”.
Such was the extent of that relationship that John Holland officials suspected the CFMEU would have a “substantial amount of knowledge around proposed government tenders and input” in respect of the tender process.
“We are thus particularly mindful of the optics in our interactions with union stakeholders,” the 2017 email said.
Four years later, the construction company noted that “the CFMEU are emboldened by their success on major infrastructure projects,” and later in 2021, that they “enjoy a significant level of influence within the state government”.
“It is a level of influence not seen in previous years and is unlikely to diminish.”