Snowy Hydro 2.0 has blown out to 12 times its original cost – but the CEO says it ‘could have been worse’
Özet haber: New projections by the Snowy Hydro company show tunnelling work is now 65% finished, but the completion date has been pushed back to 2029

New projections by the Snowy Hydro company show tunnelling work is now 65% finished, but the completion date has been pushed back to 2029
Get our breaking news email, free app or daily news podcast
The cost of Snowy Hydro 2.0 has blown out to as much as $25bn, with a major reassessment finding the long-delayed renewable energy project will not be completed until the end of the decade.
First touted by the Turnbull government in 2017 with a price tag of $2bn, the cost of the project in the Kosciuszko national park has increased dramatically over time. In 2023 it was revised to almost $13bn, with construction due to completed by the end of 2028.
But new projections by the Snowy Hydro company, released on Thursday night, shows it will now cost at least $22.2bn, with contingency for a further increase to $25bn.
Machine tunnelling is now 65% complete, and major excavations are in their final stages. Work to build the new underground power station is under way, with about 5,000 people at work on the project.
But the project reset shows Snowy 2.0 won’t be completed and fully commissioned until 2029.
The Albanese government plans to announce additional project oversight and financing structures for Snowy 2.0 in coming weeks. Another injection of taxpayer funds is expected, along with possible private financing components.
Turnbull government calls the plan a $2bn intervention in the energy market, with completion date expected by 2026-27
Commonwealth says it will buy out state government shares in Snowy Hydro Limited
Board approves feasibility study which estimates the cost at between a $5.4 billion ‘low case’ scenario a $6.9 billion ‘worst case’
Board approves a final investment decision, with a $6.1bn cost estimate
NSW government gives planning approval for exploratory works
Third tunnel boring machine, known as Florence, commissioned
Chief executive and managing director Paul Broad resigns
Florence becomes stuck after hitting soft ground 150m into a 15km tunnel excavation. Remains stuck for nearly a year
Expected total cost increased to $12 billion and completion date pushed out to 2028
Snowy Hydro says it expects another major cost overrun and orders a reassessment of the project
Total cost expected to reach $25 billion, with completion date pushed to late 2029
Beset by challenges – including major delays when a specialist boring machine became bogged and wedged in hard rock – the project’s timeline and extraordinary cost overruns have been blamed on its unique nature, significant risk and technical complexity.
The boring machine, known as Florence, is still not yet at the halfway point of its 15km tunnel work.
Principal contractor, Future Generation Joint Venture (FGJV), also faced “cost estimation challenges”, according to the company.